Dartmouth Road Reconfiguration

Thanks @MajaHilton & @brencud for the replies both seem really helpful to me :slight_smile:

One supposes that if parking in adjacent streets becomes a problem then the only solution will be CPZ?

I posted this elsewhere ages ago on this subject.

In a bout of laziness, but also to avoid the sudden rain shower I caught a bus on Saturday from Kirkdale with the intention to get off by the Capitol. I was amazed at just how the traffic crawled when we hit the shops in Forest Hill. Furthermore, with the huge gap between the Dartmouth/Thornberry stop and the one by the station I had no hope of abandoning my red ship when I found the traffic came to a stand still. Thankfully my bus driver took pity and opened his doors, but that is not supposed to happen.

Any improvement on that is an improvement for all. So I’m sorry if a few cars may be displaced but for me moving people is the priority.

3 Likes

Dare I say this convo seems to have lost its direction a bit?

1 Like

@anon64893700 is right and we need to do a little clear up here (splitting off one or two tangential conversations). Will tend to this tomorrow. Please shout now if you’d prefer we left this topic intact. We can always start a new topic for D Rd and close this one.

1 Like

Will the road works actually help the way traffic slows down on Dartmouth Road at approximately the swimming pool on the way to London Road? I have to take the bus that way daily and it can add a long time to the journey – especially frustrating if you hope to get to the station but can’t get off, but also if you’re staying on the bus. If I understand the plans, the road will not be widened despite needing to be – have I got this right? In that case, I can’t see the point of the expense and disruption.

I’m by all means not an expert on these works. I understand though an extra bus stop is to be added between the station and Thornberry. So for those times there is congestion you’ll be able to easily get off and walk the rest of the wa.

The improvements are also about improving the pedestrian experience which hopefully will encourage more people to the shops.

1 Like

Assuming parking controls are effective, the new road markings will mean that we don’t have the situation where buses can’t pass each other, and so there should be less congestion.

1 Like

We can but try Brendan xx

Timetable for improvements work has now been made available and will be delivered to residents in the immediate vicinity.

Work begins on 2nd May 2017 and will be completed in March 2018. Full road closure for 6 weeks from 9th January.

1 Like

Hopefully they’ll find time to fix this problem, which I told TfL about a year and a half ago…

No. That is a different project, that I hope might happen in 2019!

I’d say it is on their optional fix list along with permanently fixing the water leak.

Zoom in to see this image of the full plans:

(The Forum is better at handling big images than Blogger or Facebook.
Thanks @anon5422159 for a good forum!)

4 Likes

Yes can see it very clearly zoomed on my iPhone.

It looks like no work is scheduled from 4th December to 8 Jan 2018 for Christmas moratorium.

What is also not in the letter is the contingency period for overrunning of 49.5 days.

2 Likes

Really good to keep the road open during the busiest shopping month.

2 Likes

How do we get stock delivered to our shops during the 6 week Road closure?

Sherpas.

3 Likes